Public Service Commission approves first two phases of Propel's environmental management and construction plans

Posted

The New York State Public Service Commission approved two phases of construction plans for the Propel NY Energy transmission project on Nov. 19, advancing preparations for the infrastructure project despite continued objections from local officials and residents.

The commission approved Phases 1 and 2 of the project’s environmental management and construction plans, which outline preliminary construction activities and environmental protections for portions of the roughly 90-mile underground and submarine transmission network. 

The project, developed by New York Transco and the New York Power Authority, will connect nine existing or proposed substations across Suffolk, Nassau, Queens, the Bronx and Westchester counties. 

“The combination of these projects together represent tremendous enhancements to the reliability of the interconnected grid consumers depend on,” PSC Chairman Rory Christian wrote in a statement. “Achieving the state’s climate goals while preserving grid reliability and affordability for all New Yorkers hinges on the availability of infrastructure to transport power to meet demand across the state.”

The first phase of the plans authorizes tree clearing at the new Barrett and Shore Road substations in Nassau County, the new Ruland Road Substation in Suffolk County, and the Shore Road landfall in Glenwood Landing. Tree clearing will be subject to seasonal restrictions, and Propel officials confirmed that it will not take place at Shore Road until next fall.

Phase 2 addresses the installation of underground conduit using horizontal directional drilling, at Shore Road and the Hudson Park and Beach landfall in New Rochelle. 

The PSC determined that the plans contain provisions intended to ensure safe and environmentally compatible site preparation, and that its orders addressed public comments.

However, Bruce Kennedy, Sea Cliff’s village administrator, said that village officials remain dissatisfied with how regulators addressed their concerns, particularly those involving Hempstead Harbor and the project’s potential effects on existing public and private uses of the waterfront. The village’s review of the commission’s orders, Kennedy said, found that relatively few of its objections resulted in changes to the approved plans.

“So all the stuff takes a lot of reading, comparison, and trying to figure out which of our comments did they address,” he said, “and they’re very careful to dance around issues and not respond to them.”

One outstanding concern involves ownership of underwater property where construction activity could take place. The village has repeatedly requested a survey map identifying underwater property boundaries and the proposed construction areas. That information, Kennedy said, is necessary to determine whether the project could interfere with swimming, boating, fishing and shellfishing in the harbor.

“If they put these [transmission] cables on properties that we own that become declared no-anchorage areas, no-fishing areas, no-swimming areas, they’re going to forever prohibit our current lawful uses and enjoyment of the harbor,” he said, “and that point has been clear to them for close to two years now.”

Kennedy warned that if the cables can’t be buried to a sufficient depth, the Coast Guard could designate portions of the harbor as no-anchor zones, potentially restricting recreational boating.

He also questioned why the commission left the responsibility for resolving underwater property issues to Propel rather than requiring the necessary information before approving the construction plans.

Another concern involves the potential effects of horizontal directional drilling on shellfish populations. Kennedy said that the village has requested a comprehensive, harbor-wide survey to establish the current locations of shellfish and better assess potential environmental damage. He added that the village has relied on research conducted by Cashin Associates, an engineering firm with extensive experience in Hempstead Harbor, but believes Propel has not adequately addressed discrepancies between the competing assessments.

Christine Panzeca, a Glen Head resident and a vocal opponent of the project, also criticized the approval process, arguing that the commission’s decision further demonstrates what she considers inadequate public participation.

“I think what we’re seeing solidifies the fact that we are participating in a perfunctory, arbitrary and capricious process,” Panzeca said, “and it further sets the record for future review.” 

Additional regulatory approvals remain necessary before construction can begin, including a water quality certification and authorization from the Army Corps of Engineers.

Propel officials, meanwhile, welcomed the commission’s decision, and announced the selection of contractors and equipment suppliers for the initial construction phases in a statement on Nov. 19. The companies anticipate beginning initial site work in early 2027, pending additional approvals. The project is expected to take roughly four years to complete.

The PSC’s approval follows a new reliability assessment from the New York Independent System Operator, which claimed that Long Island’s electric reliability could become deficient as early as summer 2030 without the Propel project.

The project’s water quality certification has also faced delays since the PSC issued the certificate on Oct. 2, only to withdraw it on Oct. 19 following objections from Sea Cliff officials and other critics. Propel has since submitted a new application, and the approval process for the certification has been delegated to the state’s Office of Renewable Energy Siting and Electric Transmission. Tuesday was the last day to make comments on the water quality certification process.

Panzeca and Kennedy, along with NYISO, Transco and New York Power Authority representatives, testified Monday before the State Assembly Committee on Corporations, Authorities and Commissions. Kennedy emphasized that one question that continued to be asked by Assembly members was whether, knowing that the original wind projects that the Propel Project had been approved to support would be canceled, the agencies would still have selected it. 

“They wouldn’t answer the question,” Kennedy said.