Q. I’m waiting months for a permit, and they keep asking for added notes and plan changes, but not all at once. It’s a complete runaround. Why is this happening? My business is losing money, and I’m losing patience.
A. Many years ago, the legendary CBS News anchor Walter Cronkite ended each broadcast with, “And that’s the way it is.”
The reasons for your delay are multi-faceted, public and private, starting with poor communication by both. Regulations and procedures are part of the problem. Ignoring regulations makes the process grind to a halt. You can complain about how long it takes, but the truth is that many people, in and out of government, can be financial killers. Businesses sit stagnant. Homeowners can’t move on with their lives; money is lost to increased material costs during the permit process. This encourages people to avoid getting permits, and then they get caught.
Bigger building departments clog their systems by sending unclear notes instead of specifically identifying items that need to be addressed, slowing the process while people scramble to figure out what the cryptic objections meant. (At least they aren’t scribbled like they used to be, before computerization.) That’s just the way it is.
You have an idea of what you want, but no idea of the tons of requirements to be met, the seemingly random steps to climb, one at a time. To smooth out the process, start with a good, readable legal survey description of your property. Keep in mind that many people believe that old building department plans are accurate, but 90 percent of the time, those plans were not followed by constructors, who treated them like suggestion and deviated, or changes were made without filing for permits. That slows the process, and the design professional’s process takes longer.